Templeton, S.R., Dumas, C., Sessions, W.T. 2008. Estimation and Analysis of Expenses of Design-Bid-Build Projects for Stream Mitigation in North Carolina. Dept. of Applied Economics and Statistics, Clemson University, Clemson, SC.
Assessment, costs, mitigation, restoration, stream
http://cherokee.agecon.clemson.edu/curr0801.pdf
The regulatory authority to require stream mitigation in North Carolina has now been in place forĀ 10 years. The goal of this study was to provide EEP officials with objective information that they could use to improve management of projects for stream mitigation. EEP has spent or committed to spend $46.34 million for 45 design-build or design-bid-build projects to restore or enhance 191,374 ft. of streams. Expenses per foot are $242.12.